A field conversation with 20 year veteran Jim Olmstead, Chemical Injection & Automation Expert, TXAM Pumps.
Every fall, the same question arises across every shale play where TXAM Pumps operates: is your chemical injection system truly ready for the first freeze, or are you about to find out the hard way?
We sat down with Jim Olmstead, who spends his days in the field doing exactly this kind of prep work, to talk through what really causes cold-weather failures, and what separates operators who sail through methanol season from the ones scrambling after the first cold snap.
It’s Rarely the Chemical, It’s the System Around It
The good news, according to Olmstead, is that the chemical itself usually isn’t the problem. “The chemical, a lot of times, is already winterized, or they’ll have winterized versions available,” he explained. Corrosion and scale packages typically come with a freeze point built in specifically so they won’t gel or crystallize in the line.
Where things go wrong is everything around the chemical: the lines, the check valves, and any exposed metal on the suction or discharge side. “Any of the exposed metal, just like when bridges freeze first in an ice storm, it’s the same thing across your suction check, your discharge check, or your suction line from the tank,” he said. If a corrosion or scale package’s freeze point isn’t low enough for how cold it actually gets on location, that’s where you’ll see it fail first.
That’s also why “methanol season” is really its own category of prep. Once temperatures drop far enough, operators start injecting methanol specifically to keep compressors and any high-pressure-differential equipment from icing up. “Most of the time when we talk about methanol season, we’re talking about pumping actual methanol to prevent freeze-ups on equipment,” Olmstead said, separate from, and in addition to, whatever corrosion or scale chemistry is already running.

The Winterization Prep Window for Methanol Systems
In Texas, the first real cold front tends to hit in late October or November, but Olmstead’s advice is to start checking systems two to three months ahead of that, not the week before. “If you’re really actively managing your account, you need to be checking your methanol and doing your systems checks and all the preventative maintenance two and three months before your first freeze,” he said. “There might be thousands of wells to go check, and you can’t do that overnight, so it’s better to start early.”
He pointed to one end-user as an example of doing this well: they buy methanol in bulk and have lease operators run systematic checks, confirming there are no leaks, that inline checks aren’t blown out, and that everything’s in good working order, well before the first freeze hits. “If they’ve already done some work and they’ve already been out there visiting and doing preventive maintenance on these systems, they’re going to find it’s a lot smoother transition after that first freeze.”
One practical tip Olmstead shares often with end users: when you’re purchasing your scale/corrosion package for wellhead chemistry, buy the methanol setup at the same time. “Not only is it under AFE that way, but it’s already set, filled up, and ready to go for when we do get the first cold snap. It’s not an afterthought, it’s building it intentionally, because they’re going to need it anyway.”
“Start winter preparation 2 to 3 months before the first freeze. Check valve failures are the #1 cause of lost injection during winter freezes. Replacing worn O-rings in idle or primary check valves and performing drawdown tests before cold weather saves thousands in emergency repairs.”
Jim Olmstead, TXAM Pumps
What a Pre-Freeze Check Actually Looks Like
Walking through a real example, TXAM crews currently doing preventive maintenance on another end-users locations running solar methanol setups, Olmstead broke down what a proper check covers:
- Charging system. On solar setups, confirm the charge controller and panel are actually putting out what they should.
- Pump function. Fire the pump up and make sure it turns on and runs like it’s supposed to.
- Voltage. Check both the solar panel output and battery voltage (more on the exact numbers below).
- Drawdown test. Confirm the pump is actually moving the volume it’s supposed to.
- Check valves. Verify all checks – suction, discharge, inline, are functioning, not stuck or worn out from months of sitting idle.
That last point matters more than people expect. “It’s been sitting there for nine months, not being utilized, and they just go over and flip it on and expect the Chemical Injection System to turn on,” Olmstead said. “A lot of times with inline check valves, you’ve had nothing sitting in there for months and months, not moving, kind of dry-rotting the O-rings.” Bad batteries and worn check valves are the two most common reasons a system that “should” work doesn’t, on the first real cold day.
TXAM also has a mobile preventive maintenance checklist app (built by TXAM’s very own Luke Goetz) that walks a technician through this same list in the field, packing, plungers, check valves, solar system, voltage, tank size, originally built for methanol systems but usable on any chemical injection setup.
To help your team get ahead of the cold, we put together a practical Preventative Maintenance Checklist your techs can take straight to the field to winterize solar and methanol systems across the shale plays.
Solar-Powered Chemical Injection in Winter
If your methanol or chemical injection system runs on solar, winter changes the math a little. Solar output depends on hours of direct sunlight, and winter means shorter days and a lot more overcast weather. “You have to watch the sizing on these solar panels,” Olmstead said. “You want to go with bigger solar panels if at all possible,” ideally something accounted for when the system is originally installed, not something you’re scrambling to fix mid-winter.
For voltage checks specifically, Olmstead’s benchmarks are:
- Solar panel output: 18–21 volts
- Battery: around 13 volts
Cloudy, overcast days will still charge the battery, just not as efficiently as a clear summer day, so a wet winter (like the one currently forecast) is worth planning around, not just the cold itself.
Once the Freeze Hits: What to Watch For
Once winter actually arrives, Olmstead says the checks become quicker and more visual:
- Packing leaks – usually a quick visual check.
- Battery voltage on solar systems, since batteries are the weak point in cold weather.
- Visible ice at the injection point. “The good thing about a freeze is you get a visual representation. If that line is freezing, you’ll actually see it freeze, you’ll actually see an ice block build up right where there’s a pressure differential, and you’ll know you’re not getting injection.”
A useful troubleshooting trick for systems with temperature-probes: many setups won’t fire until the temperature probe hits its set point, which makes it hard to verify the system works ahead of time. Olmstead’s workaround, unplug the temperature probe so the system acts like a normal timer, run a drawdown test to confirm it’s working correctly, then plug the probe back in. “As soon as it gets cold enough, you know it’s going to work.”
The Biggest Mistake You Can Make
Asked directly what trips people up most, Olmstead didn’t hesitate: skipping the preventive maintenance and assuming a system that’s been idle for nine months will just turn on and run. It usually does, but “usually” is exactly the gap that turns into an emergency service call during the first freeze of the year, when every other operator in the basin is calling for the same thing.
The operators who avoid that scramble are the ones treating methanol readiness as a fall task, not a winter emergency, checking systems two to three months out, building methanol setups into the initial AFE alongside scale/corrosion packages, and doing the hands-on verification (voltage, drawdown, check valves) before the cold arrives, not after.
Get Ahead of the First Freeze
If your chemical injection or methanol systems haven’t had a preventive maintenance check yet this season, now is the window Olmstead recommends, before the first cold front, not during it.
Visit our Locations page to connect with your local TXAM Pumps team about a pre-freeze system check, or give your local TXAM representative a call about setting up methanol injection before the cold arrives.
Article By Shana McGuire, based on an interview with Jim Olmstead, Chemical Injection & Automation Expert at TXAM Pumps.